Thursday, June 30, 2011

Friday, June 24, 2011

The contractor has completed the punch list work this week and the construction work is finished.

Thursday, June 16, 2011

The contractor has completed a majority of the punch list work this week and is anticipated to complete the punch list work next week.

Friday, June 10, 2011

Pavement markings and signs were installed early this week. Only pavement patching and punch list work remain to be completed for this project. This project is anticipated to be complete in June.

Friday, June 3, 2011

Only pavement patching, striping, signing, and punch list work remain to be completed for this project. Striping is scheduled for Monday June 6 (weather dependent). This project is anticipated to be complete in June.

Friday, May 27, 2011

The contractor finished planting the parkway trees early this week.
Only pavement patching, striping, signing, and punch list work remain to
be completed in June.

Monday, May 9, 2011

Techny Trail construction is nearing completion. Only tree planting, pavement patching, striping, signing, and punch list work remain to be completed in May.

Saturday, April 30, 2011

Techny Trail construction is nearing completion. Only tree planting, pavement patching, striping, signing, and punch list work remain to be completed in May.

Thursday, April 21, 2011

Techny Trail construction is nearing completion. Only tree planting, pavement patching, striping, signing, and punch list work remain to be completed in late April or early May.

Friday, April 15, 2011

Techny Trail construction is nearing completion. The contractor (A. Lamp Concrete Contractors) has been on site this week watering the newly placed sod. Only tree planting, striping, signing, pavement patching and punch list work remain to be completed in late April or early May.

Friday, April 8, 2011

A. Lamp Concrete Contractors has completed the installation of sodding the parkway on either side of the bike path. Signing and striping are anticipated to be completed in the next couple of weeks.

Friday, April 1, 2011

A. Lamp Concrete Contractors has completed the installation of the concrete trail. A. Lamp will continue with topsoil placement this week and into early next week. A. Lamp is scheduled to place sodding next week (weather permitting).

Monday, March 28, 2011

Things are really moving out there!

Many of you may have noticed that the contractor began placing the concrete bikepath today. Much of the conrete bikepath will be in place by Tuesday March 29! This work has really been accelerated and everyone will be able to enjoy walking and riding their bicycles on the new path very soon!

Thursday, March 17, 2011

Work has started!

Work on Techny Trail started this Tuesday with the removal of sidewalk
along Lehigh Avenue from the Metra parking lot entrance on Lehigh Avenue
to the bridge spanning East Lake Street. The Contractor will begin
installing the storm sewer addtions on the project this week, as well.
Construction trucks will be parked along Lehigh Avenue and there will be
flaggers to direct traffic.

The taxi stand on Lehigh Avenue across from the train station is
temporarily relocated to the cul-de-sac on Prairie Street on those dates
which construction activity on Lehigh across from the train station will
occur.

Project construction is anticipated to be complete by April 1st (weather
dependent).

Tuesday, March 8, 2011

Construction season is here!

This proposed 10 foot wide concrete biketrail on the west side of Lehigh Avenue from Chestnut Avenue to Glenview Road is planned to start construction within the next two weeks (weather dependent) and is anticipated to be completed by early May 2011. This project was funded through a federal CMAQ grant and will complete the portion of the Techny Trail between The Glen Metra station to the north and the Metra station located in downtown and will provide opportunities for future bike lanes and/or paths extending south, east, and west of Glenview Road and Harlem Avenue as outlined in the Village’s Bicycle and Sidewalk Master Plan. This bike trail also extends to the new Glenview Public Library.