Saturday, April 30, 2011

Techny Trail construction is nearing completion. Only tree planting, pavement patching, striping, signing, and punch list work remain to be completed in May.

Thursday, April 21, 2011

Techny Trail construction is nearing completion. Only tree planting, pavement patching, striping, signing, and punch list work remain to be completed in late April or early May.

Friday, April 15, 2011

Techny Trail construction is nearing completion. The contractor (A. Lamp Concrete Contractors) has been on site this week watering the newly placed sod. Only tree planting, striping, signing, pavement patching and punch list work remain to be completed in late April or early May.

Friday, April 8, 2011

A. Lamp Concrete Contractors has completed the installation of sodding the parkway on either side of the bike path. Signing and striping are anticipated to be completed in the next couple of weeks.

Friday, April 1, 2011

A. Lamp Concrete Contractors has completed the installation of the concrete trail. A. Lamp will continue with topsoil placement this week and into early next week. A. Lamp is scheduled to place sodding next week (weather permitting).